I-405 Improvement Project construction alert: Week of July 15



What
Falsework construction, which includes installing timber and steel beams to support construction of the new Magnolia Street bridge.
Where

Adjacent to Magnolia Street, on the northbound (NB) side of I-405. I-405 will be closed between Warner Avenue and Magnolia Street

Additional Closures:

  • NB I-405 loop on-ramp from Magnolia Street
  • NB I-405 on-ramp from Warner Avenue
Detours will be in place, and signs will be posted to guide motorists around the closures. Motorists should expect delays and use alternate routes if possible.
 
When
As early as Monday, July 15 to Thursday, July 18: 11 p.m. to 5 a.m.  NB I-405, the NB I-405 loop on-ramp from Magnolia Street, and the NB I-405 loop on-ramp from Warner Avenue will be closed
 
Detour
NB I-405 Detour:
Warner Avenue → Beach Boulevard → Beach Boulevard on-ramp




What
Crews will install temporary shoring or bridge supports for the new side of the bridge.
Where
Bolsa Avenue, between Goldenwest Street and Chestnut Street
When
As early as 10 p.m. to 5 a.m., Monday, July 15 to Friday, July 19
 
Detour
Eastbound Bolsa Avenue Detour:
Bolsa Avenue → Goldenwest Street → Hazard Avenue → Hoover Street or Beach Boulevard → Bolsa Avenue

Westbound Bolsa Avenue Detour:
Bolsa Avenue → Beach Boulevard → Hazard Avenue → Goldenwest Street → Bolsa Avenue 





What
Crews will continue hauling out materials from concrete demolition and removal.
Where
Center median of I-405, near SR-22/I-605 interchange

When
Ongoing, 10 p.m. to 5 a.m., through July 16 on weeknights
 


What
Electrical work and street improvements
Where
Warner Avenue, between Brookhurst Street and Bushard Street

When
Ongoing, through Fall 2019, 6:30 a.m. to 4 p.m., on weekdays and Saturdays
 
Warner Avenue will be reduced to one lane intermittently between Brookhurst Street and Bushard Street
 


What
Ocean View channel widening 
Where
NB I-405, between Warner Avenue and Magnolia Street
When
Ongoing as of May 6, 7 a.m. to 4 p.m., and will continue on weekdays
 
Crews may also work at night.
 


What
Crews will remove the falsework from the Slater Avenue bridge.
Where
Adjacent to Slater Avenue, on the northbound (NB) and southbound sides of I-405


Closures:

  • NB I-405, between Brookhurst Street and Magnolia Street
  • NB I-405 loop on-ramp from NB Brookhurst Street
  • NB I-405 on-ramp from SB Brookhurst Street
  • SB I-405, between Magnolia Street and Brookhurst Street
  • SB I-405 loop on-ramp from Magnolia Street
  • SB I-405 on-ramp from EB Warner Avenue
  • SB I-405 off-ramp onto SB Brookhurst Street
  • SB I-405 loop on-ramp from SB Brookhurst Street
NB and SB closures will not be implemented concurrently.

Detours will be in place, and signs will be posted to guide motorists around the closures. Motorists should expect delays and use alternate routes if possible.
 
When
This work has been postponed to a later date.
Detour
All closures and detours will be included in our interactive map and on our closure list.


What
Bridge construction activities
Where
NB Bolsa Chica Road will be reduced to one lane intermittently between Duncannon Avenue and Garden Grove Boulevard
When
Ongoing, 9 a.m. to 3 p.m., on weekdays
 


What
Bridge construction activities
Where
NB Magnolia Street will be reduced to one lane intermittently between the Boomers driveway and Heil Avenue
When
Ongoing, 9 a.m. to 3 p.m., on weekdays
 

What
Daytime pile and steel plate installation for temporary shoring
Where
Along the Magnolia Street SB I-405 off-ramp
When
As early as Thursday, July 18 to Friday, July 25, 6:30 a.m. to 4 p.m., on weekdays.
 
Crews may conduct pile installation activities at night.
 

What
Daytime pile installation activities
Where
Adjacent to the Fairview Road bridge on the NB and SB sides of I-405, and in the center median of the freeway
When
Ongoing as of Monday, July 1, 6:30 a.m. to 4 p.m., for approximately two months, on weekdays and Saturdays.
 
Crews may conduct pile installation activities at night.
 

What
Daytime pile installation activities
Where
Adjacent to Westminster Boulevard, in the center median of the freeway
When
Ongoing as of Tuesday, July 2, 7 a.m. to 4 p.m., for approximately two more weeks, on weekdays
 
Crews may conduct pile installation activities at night.
 

What
Underground utility work
Where
Spencer Avenue, between Pacific Street and Langley Street


Crews reduced the width of Spencer Avenue, however, it remains open with one lane in each direction.

When
Ongoing, 7 a.m. to 4 p.m., and will continue for approximately two weeks, on weekdays
 
Crews may also work at night.

What
Underground utility work
Where
SB Bushard Street, between Warner Avenue and La Luna Avenue

 

SB Bushard Street will be reduced to one lane intermittently between Warner Avenue and La Luna Avenue.
When
Ongoing, 6:30 a.m. to 4 p.m., and will continue for approximately two weeks, on weekdays
 
Crews may also work at night.

What
Underground utility work
Where
On Heil Avenue, adjacent to NB I-405
When
Ongoing, 6:30 a.m. to 4 p.m., and will continue for approximately two months
 
Crews may also work at night.
 
The work zone will be in the alley adjacent to the pedestrian overcrossing.
 

What
Underground utility work
Where
On the Goldenwest Street bridge over I-405, between Sowell Avenue and just north of Bolsa Avenue.
When
Ongoing, 7 a.m. to 4 p.m., on weekdays, through mid-December
 
Crews may also work at night.

What
Crews demolished the remainder of the existing sound wall adjacent to SB I-405 along Milan Street.

 

Crews are now working on the foundation of the new wall.

Please be advised that this work may be loud.
Where
Southbound I-405, along Milan Street, between Bolsa Chica Road and Stratford Avenue.
 
When
Activities will occur approximately 7 a.m. to 4 p.m. and 10 p.m. to 5 a.m.

 

Crews will haul out materials behind freeway lane closures, which can only be done at night.

 



What
Crews are working on the foundation of the new wall and loading out material.
Where
SB I-405, adjacent to Bolsa Chica Road
When
Ongoing, 7 a.m. to 4 p.m., on weekdays 
 
Crews may also work at night.
 

What
Crews demolished the remainder of the existing sound wall adjacent to SB I-405 between Milan Street and Springdale Street.

Crews are now working on the foundation of the new wall.

A temporary sound barrier will be in place during construction of the new sound wall.

Please be advised that this work may be loud.
Where
Southbound I-405 between Milan Street and Springdale Street.
 
When
Activities will occur approximately 6:30 a.m. to 4 p.m. and 10 p.m. to 5 a.m.

Crews will haul out materials behind freeway lane closures, which can only be done at night.

What
Crews demolished the remainder of the sound wall adjacent to NB I-405 between Springdale Street and Valley View Street.

Crews are now working on the foundation of the new wall.

A temporary sound barrier will be in place for the duration of construction of the new sound wall.
 
Please be advised that this work may be loud. 
Where
NB I-405, between Springdale Street and Valley View Street.
 
When
Demolition activities are ongoing as of Monday, May 6. 

Activities will occur approximately 6:30 a.m. to 4 p.m. and 10 p.m. to 5 a.m. 

Crews will haul out materials behind freeway lane closures, which can only be done at night.

What
Crews are building the new wall and loading out material.

 

Where
Along SB I-405 near Talbert Avenue, adjacent to LA Fitness

When
Ongoing, during the day and at night on weekdays

What
Crews are working on the foundation for the new wall and loading out material.

 

Where
Milan Street, between approximately Stratford Avenue and 200 feet south of Lowell Circle.

When
Ongoing, during the day and at night on weekdays 
 

The duration of this work may change depending on site conditions. Please be advised that this work may be loud. Dates and times are subject to change due to unforeseen operational factors or inclement weather.

To view all project closures and detours, please visit the interactive map  or click here for a pdf list. 
 
This article was released by the Orange County Transportation Authority.