NEW! Bushard Street Bridge Demolition
The bridge will be demolished over two weekends under full freeway closures. Additional demolition activities will occur during weeknights under freeway lane closures and on weekdays.
Please be advised that this work may be loud.
Bushard Bridge Demolition Night One:
11 p.m. Saturday, Sept. 14, to 9 a.m. Sunday, Sept. 15:
- NB I-405 closed between Brookhurst Street and Warner Avenue
- SB I-405 closed between Warner and Brookhurst
Bushard Bridge Demolition Night Two:
11 p.m. Saturday, Sept. 28, to 9 a.m., Sunday, Sept. 29:
- NB I-405 closed between Brookhurst and Warner
- SB I-405 closed between Warner and Brookhurst
Talbert Avenue Bridge Demolition Continues
- Scheduled for 10 p.m. to 5 a.m., Monday, Sept. 9 to Friday, Sept. 13
Falsework Removal at Slater Avenue Continues
- Scheduled for 11 p.m. to 5 a.m., Monday, Sept. 9 to Friday, Sept. 13
Closures set at north end of project for sign structure removal
- Scheduled for midnight to 4 a.m. the night of Friday, Sept. 13
Construction Activities
Harbor Boulevard
Crews will install piles for the foundation of the widened I-405 bridge over Harbor Boulevard.
- Scheduled to begin Monday, Sept. 16, 7 a.m. to 4 p.m., and continue for several weeks
Harbor Boulevard will be reduced to two lanes in each direction and left-turn movements will be restricted from the NB I-405 off-ramp for Saturday activities.
- Scheduled for Saturday, Sept. 21, 7 a.m. to 9 p.m. and again on Saturday, Sept. 28, 7 a.m. to 9 p.m.
Bolsa Chica Road
Crews will continue installing piles for the foundation of the new bridge adjacent to SB I-405.
- Ongoing, 7 a.m. to 4 p.m.