REMINDER! Southbound (SB) and Northbound (NB) Freeway Closures for Westminster Boulevard bridge falsework construction
Southbound Closure Details:
SB closures are scheduled for 11 p.m. to 5 a.m. weeknights, Monday, Jan. 27, to Tuesday, Feb. 4.
Dates and times are subject to change due to unforeseen operational factors or inclement weather.
SB Closures:
- SB I-405 between Springdale Street and Edwards Street
- SB I-405 loop off-ramp to Westminster
- NB I-405 loop off-ramp to Westminster
Northbound Closure Details:
NB closures are scheduled for 11 p.m. to 5 a.m. weeknights, Wednesday, Feb. 5, to Friday, Feb. 14.
Dates and times are subject to change due to unforeseen operational factors or inclement weather.
NB Closures:
- NB I-405 between Edwards and Springdale
- SB I-405 loop off-ramp to Westminster
- NB I-405 loop off-ramp to Westminster